
RENOVATIONS & UPGRADES
Construction Updates
As of
August 19, 2026
-
Construction in 181 and 187 Hoyt Street (B3) was completed on April 6, 2026.
-
Construction in 175 Hoyt Street (B1) was completed on July 31, 2026.
-
Construction in 417 Baltic Street (B4W) began on July 14, 2026

phase
Phase 1
(IN-UNIT RENOVATIONS)
175 Hoyt Street (B1)
181-187 Hoyt Street (B3)
417 Baltic Street (B4W)


Current Activity

-
Resident relocations at 417 Baltic Street (4W) are complete on Floors 6 through 14, with construction activities underway in those apartments.
-
Distribution of 30-day RANV notices continues for residents on the lower floors at 417 Baltic Street (4W). Relocations for these residents are scheduled to begin in mid- to late September.
-
Scheduled water shutdowns continue every Tuesday at 417 Baltic Street, with residents receiving advance notice prior to each shutdown.
-
The Resident Engagement Team and Relocation Coordinators continue to provide residents with ongoing communication and support throughout the relocation process.

What RESIDENTS CAN Expect
SERVICE IMPACTS
-
Temporary water and heat interruptions are expected as part of the work.
-
Residents will receive at least 72 hours’ advance notice before any shutdown.
-
Whenever possible, interruptions will be scheduled during regular work hours and limited to one building at a time.
-
These interruptions are expected approximately every five business days.
OPERATIONS
AND
DAILY CONDITIONS
-
Construction staffing has increased across the development beginning in February 2026.
-
Work will take place floor by floor, starting at the top and moving downward, in groups of 8 apartments at a time.
-
Common areas will be cleaned and maintained daily throughout construction.


SCOPE OF WORK

Kitchen Renovations
Bathroom Renovations
Hazardous Material Abatement
Heating Optimization
Elevator Modernization
Ventilation
Pest & Waste Management
Plumbing
Section 504
Apartment Conversions







